Common late-stage changes in healthcare construction projects and how to avoid them

Dan Mason from Pulse Consult explains how to prevent the "last-minute pivot" and keep healthcare projects on track

Major healthcare infrastructure projects have never been straightforward, characterised by complex and ambitious delivery programmes with extensive stakeholder networks. Paired with multiple NHS critical incidents declared over the past year, it is increasingly crucial to balance project variables, with little room for error.

This pressure is also translated into policy changes, with the Public Accounts Committee's April 2026 review of the New Hospital Programme highlighting the scale of the challenge, extending the programme to 2045/46.

Against this backdrop of increasing pressures, Dan Mason, Director and project manager at construction consultancy Pulse Consult, notes one of the most challenging aspects of major hospital infrastructure delivery is managing changes, especially those that emerge later down the line.

By investing time at the initial planning stages where stakeholders are engaged early, information-sharing is prioritised and shared ownership is agreed, the likelihood of these late-stage changes can be minimised, improving project viability and patient outcomes. 

Lessons from the frontline

This front-loaded process was a fundamental approach for the effective project delivery of the Waterloo Health Centre Modular Facility. This was an urgent relocation project, with more than 14,000 patients depending on the successful and timely delivery of the temporary base to continue receiving community care.

When the stakes are high, getting the decisions right early can make all the difference in delivering the right outcome for the people who depend on it. 

When requirements shift: The post-design freeze challenge

Project management in healthcare requires a forward-looking approach to balance out the changing nature that healthcare projects are susceptible to, and this includes anticipating where designs may fall short of reflecting how a practice will operate in reality. 

With a community relying on the efficient and effective delivery of the Waterloo Health Centre to allow continued access to healthcare treatment, the project was delivered within an exceptionally compressed ten-month programme, from inception to completion.

Underscored by an accelerated timeline, one of the key late-stage change risks was the emergence of changing clinical and operational requirements after the design freeze.

To mitigate this for the Waterloo Health Centre, the project team undertook an intensive period of stakeholder engagement during the design development stage, working closely with the South East London ICB, clinical users and operational leads to rapidly define requirements. This was implemented through a series of focused design workshops, enabling key decisions from the outset. 

Pulse Consult conducted a series of focused design workshops

For accelerated healthcare projects, investing time upfront to bring stakeholders together for focused decision-making can significantly reduce the risk of costly redesign and programme delays later in the project lifecycle. Consultations are effective to a degree, but implementing clear shared ownership is crucial to ensure decisions are understood, agreed upon and carried through. 

Fibre, connectivity and commissioning challenges

Grid connection challenges are far from unique to healthcare, with the wider infrastructure sector continuing to grapple with increased electricity demand, limited network capacity and often lengthy connection timescales. 

The Waterloo Health Centre required a new statutory fibre connection to support the facility’s digital infrastructure and clinical systems. Faced with a risk that delays to the external fibre installation would impact internal data installation, ICT commissioning and ultimately operational readiness, this late-stage change would have devastating consequences - a fully constructed facility, ready to serve its community, but without the connectivity needed to function.

Considering the implications of this, project stakeholders were brought together to develop contingency plans and align installation activities with the wider programme. Careful sequencing of infrastructure works ensured that internal systems were tested and commissioning activities progressed wherever possible ahead of the final fibre connection being completed. 

Engaging utility and telecommunications providers at the earliest possible stage is vital against a backdrop of increasing project delays as a result of grid connection challenges.

Engaging utility and telecommunications providers at the earliest possible stage is vital

This can have significant downstream impacts on digital commissioning and occupation programmes, and as project delays caused by late-stage connectivity continue to hit the headlines, this is a risk that cannot be ignored. 

Co-chaired discussions that prevent delays before they begin

The project stakeholders involved in delivering healthcare projects are wide-ranging, and each group brings different priorities to the table. If these priorities are not aligned early, conflicting requirements or overlooked issues can emerge once construction is underway. 

For the Waterloo Health Centre, the build was proposed in a prominent urban location, and due to a series of co-chaired project delivery groups, it was anticipated that the appearance of a modular unit could come under scrutiny regarding its integration with the surrounding street scene. 

Recognising that this risk could translate into late-stage changes based on design objections, collaborative co-chaired project delivery groups facilitated discussions that informed the development of the building's bespoke blue graphic building wrap, designed to enhance the unit’s appearance.

By proactively encouraging discussions to allow the communication of stakeholder concerns, feedback was incorporated into the design solution from the outset, and agreement was secured without adversely impacting the programme later down the line. 

Early engagement through co-chaired delivery groups can transform potential objections into collaborative opportunities, helping projects achieve both planning support and, in this case, improved community acceptance. 

Right place, right people, right time 

With NHS England calling for a more joined-up approach to capital planning and delivery, effective project governance is becoming increasingly important to ensure investment is delivered successfully. 

Time invested from the outset will translate into clear governance structures, transparent stakeholder collaboration and agreed shared priorities, leading to fewer disruptive changes as projects progress. 

Getting the right people involved at the right time will protect project viability, maintain timelines and ensure that completed facilities meet the clinical and operational needs that they were designed to serve. 

 

 